Update the 12.0-RELEASE schedule to account for an additional week

slip to finalize works-in-progress.

Approved by:	re (implicit)
Sponsored by:	The FreeBSD Foundation
This commit is contained in:
Glen Barber 2018-10-08 15:03:19 +00:00
parent f0883ffedb
commit debbac5f62
Notes: svn2git 2020-12-08 03:00:23 +00:00
svn path=/head/; revision=52343
2 changed files with 13 additions and 13 deletions

View file

@ -108,7 +108,7 @@
<tr>
<td>&local.branch.stable; branch</td>
<td>12&nbsp;October&nbsp;2018</td>
<td>19&nbsp;October&nbsp;2018</td>
<td>-</td>
<td>Subversion branch created; release engineering continues
on this branch.</td>
@ -116,14 +116,14 @@
<tr>
<td>BETA1 builds begin</td>
<td>12&nbsp;October&nbsp;2018</td>
<td>19&nbsp;October&nbsp;2018</td>
<td>-</td>
<td>First beta test snapshot.</td>
</tr>
<tr>
<td>&local.branch.head;&nbsp;thaw</td>
<td>14&nbsp;October&nbsp;2018</td>
<td>21&nbsp;October&nbsp;2018</td>
<td>-</td>
<td>The code freeze on the &local.branch.head; branch
is lifted.</td>
@ -131,21 +131,21 @@
<tr>
<td>BETA2 builds begin</td>
<td>19&nbsp;October&nbsp;2018</td>
<td>26&nbsp;October&nbsp;2018</td>
<td>-</td>
<td>Second beta test snapshot.</td>
</tr>
<tr>
<td>BETA3 builds begin&nbsp;*</td>
<td>26&nbsp;October&nbsp;2018</td>
<td>2&nbsp;November&nbsp;2018</td>
<td>-</td>
<td>Third beta test snapshot.</td>
</tr>
<tr>
<td>&local.branch.releng; branch</td>
<td>2&nbsp;November&nbsp;2018</td>
<td>9&nbsp;November&nbsp;2018</td>
<td>-</td>
<td>Subversion branch created; future release engineering
proceeds on this branch.</td>
@ -153,14 +153,14 @@
<tr>
<td>RC1 builds begin</td>
<td>2&nbsp;November&nbsp;2018</td>
<td>9&nbsp;November&nbsp;2018</td>
<td>-</td>
<td>First release candidate.</td>
</tr>
<tr>
<td>&local.branch.stable;&nbsp;thaw</td>
<td>4&nbsp;November&nbsp;2018</td>
<td>11&nbsp;November&nbsp;2018</td>
<td>-</td>
<td>The code freeze on the &local.branch.stable; branch
is lifted.</td>
@ -168,28 +168,28 @@
<tr>
<td>RC2 builds begin</td>
<td>9&nbsp;November&nbsp;2018</td>
<td>16&nbsp;November&nbsp;2018</td>
<td>-</td>
<td>Second release candidate.</td>
</tr>
<tr>
<td>RC3 builds begin&nbsp;*</td>
<td>16&nbsp;November&nbsp;2018</td>
<td>23&nbsp;November&nbsp;2018</td>
<td>-</td>
<td>Third release candidate.</td>
</tr>
<tr>
<td>RELEASE builds begin</td>
<td>23&nbsp;November&nbsp;2018</td>
<td>30&nbsp;November&nbsp;2018</td>
<td>-</td>
<td>&local.rel;-RELEASE builds begin.</td>
</tr>
<tr>
<td>RELEASE announcement</td>
<td>27&nbsp;November&nbsp;2018</td>
<td>4&nbsp;December&nbsp;2018</td>
<td>-</td>
<td>&local.rel;-RELEASE press release.</td>
</tr>

View file

@ -55,7 +55,7 @@
</tr>
<tr>
<td>November&nbsp;2018</td>
<td>December&nbsp;2018</td>
<td>&os;&nbsp;12.0</td>
<td><a
href="&base;/releases/12.0R/schedule.html">Target